Question: Product A is made from 2 Bs and 1 C. Lead times for A, B, and C are 2, 1, and 2 weeks respectively. Currently

Product A is made from 2 Bs and 1 C. Lead times

Product A is made from 2 Bs and 1 C. Lead times for A, B, and C are 2, 1, and 2 weeks respectively. Currently there are 5 As, 10 Bs and 10 Cs on hand. It is the start of week 1 now. The master schedule calls for 20 As at the start of week 5. When and how large of an order of C should be placed? A. start of week 3, 10 Cs B. start of week 1, 5 Cs C. start of week 1, 20 Cs D. start of week 3, 20 Cs E. start of week 1, 10 Cs