Question: Progress Management What value would you report as per cent completeness of the project listed below where per cent complete = BCWP/BAC? You have to

Progress Management What value would you report

Progress Management What value would you report as "per cent completeness" of the project listed below where per cent complete = BCWP/BAC? You have to show work for full credit Activity Planned (hours) Actual(hours) Status Analysis 190 195 Done Design 145 151 Done Coding 189 20% Documentation 160 19 % 70 Testing Debugging 150