Question: Project Aurora involves 7 tasks that are summarized in the following table. Each task requires special machines. There are, however, only 3 units of special
Project Aurora involves 7 tasks that are summarized in the following table. Each task requires special machines. There are, however, only 3 units of special machines available. Apply the heuristic method to construct a project schedule to determine whether Project Aurora can be completed in seven days. (Note: To obtain full marks, you must show the final project schedule as well as the project network. Details of applying the ranking procedures are not essential.)
| Activity ID | Predecessor | Duration | Resource Requirement |
| A | - | 2 days | 2 units |
| B | A | 1 day | 1 unit |
| C | A | 2 days | 1 unit |
| D | A | 3 days | 1 unit |
| E | A | 2 days | 1 unit |
| F | E | 2 days | 2 units |
| G | B, C, D, F | 1 day | 2 units |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
