Question: Project Aurora involves 7 tasks that are summarized in the following table. Each task requires special machines. There are, however, only 3 units of special

Project Aurora involves 7 tasks that are summarized in the following table. Each task requires special machines. There are, however, only 3 units of special machines available. Apply the heuristic method to construct a project schedule to determine whether Project Aurora can be completed in seven days. (Note: To obtain full marks, you must show the final project schedule as well as the project network. Details of applying the ranking procedures are not essential.)

Activity ID

Predecessor

Duration

Resource Requirement

A

-

2 days

2 units

B

A

1 day

1 unit

C

A

2 days

1 unit

D

A

3 days

1 unit

E

A

2 days

1 unit

F

E

2 days

2 units

G

B, C, D, F

1 day

2 units

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!