Question: Project Boyz is expected to generate $30,000 each year for the next years will cost $60.000 to implement the project today. If the project required
Project Boyz is expected to generate $30,000 each year for the next years will cost $60.000 to implement the project today. If the project required rate of retumis 14.0% what is a profitability index? Round your firal answer to two decimal places (Ex 0.00