Question: Project ET, LT, TB, TB representation for the activity and for which the plan drawing is given calculate. Find the critical path. please hurry up.

Project ET, LT, TB, TB representation for the activity and for which the plan drawing is given calculate. Find the critical path. please hurry up.2. Faaliyet sreleri ve ebeke izimi aada verilen proje iin ET, LT, SB, TB deerlerini hesaplaynz. Kritik yolu bulunuz. (25p) D, 10 G, 6 Kukla 1,0 8 A, 9 J, 2 H, 3 C, 7 E, 1 Kukla 2,0 B, 11 F, 5 K, 8 , 1 3 7 Faaliyet Dm Faaliyet Sresi ET LT SB TB Kritik yol zerinde mi? 9 B 11 7 D 1-2 1-3 2-3 2-4 3-4 3-8 4-5 E F G H 4-6 10 1 5 6 3 0 0 1 2 8 Kukla 1 Kukla 2 5-8 5-7 6-7 8-9 J K 7-9