Question: Project management (1) Consider the following project: Activity A B C Immeadiate Predecessors A A B C B,C 3 G D,E 6 H C 2

Project management (1) Consider the following
Project management (1) Consider the following project: Activity A B C Immeadiate Predecessors A A B C B,C 3 G D,E 6 H C 2 Which one of the following would expedite the project? Multiple Choice Expediting E by 1 week O Expediting D by 2 weeks Expediting H by 1 week Expediting B by 1 week D E F Durations (weeks) 3 3 2 3 7