Question: Project Management A Project has been defined to contain the following list of activities along with their required times for completion. Activity Immediate Activity Weeks

Project Management

A Project has been defined to contain the following list of activities along with their required times for completion.

Activity

Immediate Activity

Weeks

Predecessors

1

Collect Requirements

2

-

2

Analyze Processes

3

1

3

Analyze Data

3

2

4

Design Processes

7

2

5

Design data

6

2

6

Design screens

1

3, 4

7

Design reports

5

4, 5

8

Program

4

6, 7

9

Test and document

8

7

10

Install

2

8, 9

  1. Draw a network diagram for the activities
  2. Calculate the earliest expected completion time.
  3. Show the critical path
  4. Calculate the Earliest Start and the Latest Start of each activity
  5. Calculate slack times for each activity

These have to be completed by hand. No MS Project. Please scan and upload a copy to Blackboard)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!