Question: Project Management A Project has been defined to contain the following list of activities along with their required times for completion. Activity Immediate Activity Weeks
Project Management
A Project has been defined to contain the following list of activities along with their required times for completion.
| Activity | Immediate Activity | Weeks | Predecessors |
| 1 | Collect Requirements | 2 | - |
| 2 | Analyze Processes | 3 | 1 |
| 3 | Analyze Data | 3 | 2 |
| 4 | Design Processes | 7 | 2 |
| 5 | Design data | 6 | 2 |
| 6 | Design screens | 1 | 3, 4 |
| 7 | Design reports | 5 | 4, 5 |
| 8 | Program | 4 | 6, 7 |
| 9 | Test and document | 8 | 7 |
| 10 | Install | 2 | 8, 9 |
- Draw a network diagram for the activities
- Calculate the earliest expected completion time.
- Show the critical path
- Calculate the Earliest Start and the Latest Start of each activity
- Calculate slack times for each activity
These have to be completed by hand. No MS Project. Please scan and upload a copy to Blackboard)