Question: Project Management Based off Earned value (EV) EV = PV of all completed work Cost variance (CV) CV = EV - AC Schedule variance (SV)

Project Management

Based off

Earned value (EV) EV = PV of all completed work
Cost variance (CV) CV = EV - AC
Schedule variance (SV) SV = EV - PV
Cost performance index (CPI) CPI = EV/AC
Schedule performance index (SPI) SPI = EV/PV
Estimate at completion (EAC) EAC = BAC/CPI
Estimated to Complete (ETC)

ETC = EAC - AC

ANSWER THIS

Fill in the variances and performance indices
BAC $ 120,000.00
Earned value (EV) $ 20,000.00
Planned value (PV) $ 22,000.00
Actual cost (AC) $ 25,000.00
Cost variance (CV)
Schedule variance (SV)
Cost performance index (CPI)
Schedule performance index (SPI)
Estimate at completion (EAC)
Estimated to Complete (ETC)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!