Question: Project Management Based off Earned value (EV) EV = PV of all completed work Answer this Instructions : Fill in Total Cost , build a
Project Management
Based off
| Earned value (EV) | EV = PV of all completed work |
Answer this
| Instructions: Fill in Total Cost , build a Ghantt Chart, and Fill in the Chart (AC, EV, PV, CPI, CV, SPI, SV) | |||||||||||||
| Activity | Predecessor | Duration (Days) | Cost/Day | Total Cost | Build a Ghantt Chart | ||||||||
| A | - | 2 | $ 300.00 | A | |||||||||
| B | A | 3 | $ 400.00 | B | |||||||||
| C | B | 3 | $ 400.00 | C | |||||||||
| D | B | 2 | $ 200.00 | D | |||||||||
| E | D | 3 | $ 100.00 | E | |||||||||
| Day 1 | Day 2 | Day 3 | Day 4 | Day 5 | Day 6 | Day 7 | |||||||
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
