Question: Project Management Based off Earned value (EV) EV = PV of all completed work Answer this Instructions : Fill in Total Cost , build a

Project Management

Based off

Earned value (EV) EV = PV of all completed work

Answer this

Instructions: Fill in Total Cost , build a Ghantt Chart, and Fill in the Chart (AC, EV, PV, CPI, CV, SPI, SV)
Activity Predecessor Duration (Days) Cost/Day Total Cost Build a Ghantt Chart
A - 2 $ 300.00 A
B A 3 $ 400.00 B
C B 3 $ 400.00 C
D B 2 $ 200.00 D
E D 3 $ 100.00 E
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7