Question: Project Management. Consider task A where (Pessimistic time) b = 10, (Most likely time) m = 8, and (Optimistic time) a = 7. What is

Project Management. Consider task A where (Pessimistic time) b = 10, (Most likely time) m = 8, and (Optimistic time) a = 7. What is the expected duration of this task? Group of answer choices 8.16 7.6