Question: help fast pls! Project Management. Consider task A where (Pessimistic time) b=10, (Most likely time) m=8, and (Optimistic time) a=6. What is the expected duration
Project Management. Consider task A where (Pessimistic time) b=10, (Most likely time) m=8, and (Optimistic time) a=6. What is the expected duration of this task? 10.00 8.00 7.66 7.83 Project Management. Consider task A where (Pessimistic time) b=10, (Most likely time) m=8, and (Optimistic time) a=6. What is the expected duration of this task? 10.00 8.00 7.66 7.83