Question: Project Management. Consider task A where (Pessimistic time) b = 10, (Most likely time) m = 8, and (Optimistic time) a = 6. What is

Project Management. Consider task A where

Project Management. Consider task A where (Pessimistic time) b = 10, (Most likely time) m = 8, and (Optimistic time) a = 6. What is the variance of this task? O 0.83 O 0.69 O 0.44 O 1.00