Question: Project Management for Design & Construction Name: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Project Management for Design & Construction Name: _____________________________
Process Mapping Workshe
et Page 3 of 4
Problem 2:
Use the empty boxes drawn below to arrange the following tasks in an order that fulfills the process description
below. Label each box and draw ALL connecting arrows.
Process Description: There are twelve (12) Tasks to this process. There are eighteen (18) boxes drawn below
for your use, however, you will only use twelve (12) of the boxes below. Place an X across the boxes you do
NOT use. Use following Tasks and their relationships to mark-up the process.
Task A1 A2 A3 A4 B1 B2 B3 B4 B5 C1 C2 C3
Task(s)
Before B1 A1 A2, B4 A3 None B1 B2 B3 A4, C3 B1 C1 C2
Task(s)
After A2 A3 A4 B5 B2, A1, C1 B3 B4, C2 A3 None C2 C3 B5
Time
(Days)423213421344

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!