Question: PROJECT MANAGEMENT Kindly construct a PERT and CPM Method to find critical path of below table Activity Description Predecessor Duration (hour) Expected Time Variance Optimistic,a

PROJECT MANAGEMENT

Kindly construct a PERT and CPM Method to find critical path of below table

Activity

Description

Predecessor

Duration (hour)

Expected Time

Variance

Optimistic,a

Most likely, m

Pessimistic, P

A

Cutting rod into shorten chunks

2

1

3

1.5

0.03

B

Drilled tunnels through the center of blanks

A

2

1

3

1.5

0.03

C

Press the blank with Press machine

B

1

1

3

1.33

0.11

D

Use the Press Machine against to make a full length and shape of a baseball bat.

C

1

1

3

1.33

0.11

E

Cutting (CNC Machine) make a thread for end cap

D

1

2

3

2.00

0.11

F

Testing the bats

E

1

3

4

2.83

0.25

G

Painting the bats

F

1

2

4

2.17

0.25

H

Assembly bats, knob and end cap

G

1

2

3

2.00

0.11

I

Inspection

H

1

2

2

1.83

0.03

J

Finishing

I

1

1

2

1.17

0.03

K

Packaging

J

1

1

2

1.17

0.03

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!