Question: *project management question* c. Assume that Systems Analysis actually finished at 8 weeks, Design Input & Output actually finished at 15 weeks, and Design Database

*project management question*
*project management question* c. Assume that
*project management question* c. Assume that
c. Assume that "Systems Analysis" actually finished at 8 weeks, "Design Input \& Output" actually finished at 15 weeks, and "Design Database" actually finished at 19 weeks. Recalculate the expected project completion time. Please provide answers in Table below. Please support your answer. d. Which activities would you focus on in order to get the project back on schedule? Explain. What is the most Critical Path now