Question: (Project Management question) Use the following Gantt chart and table to answer questions (a) and (b). 26. Use the following Gantt chart and table to
(Project Management question) Use the following Gantt chart and table to answer questions (a) and (b).


26. Use the following Gantt chart and table to answer questions (a) and (b). early start early finish late finish A 20 B 15 C 20 D5 E 10 F 10 G 15 Number of workers required daily for each activity D 0 0 B CE D Activities w E F G + 1 2 3 3 4 5 6 7 8 On this diagram, show the total daily workers required (loading) assuming early start times for all activities. Show what portion of the total labor loading each day comes from each activity. 35 30 25 20 No. Workers 15 10 5 1 2 3 3 4 5 6 7 8 (b) On this diagram, balance the loading of workers by shifting activities so that no more than 20 workers per day are needed. Assume that the project must be completed in eight days. 20 15 No. Workers 10 5 1 N 5 6 6 7 8 7 8 3 4 DAYS
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts