Question: Project management, The schedule progress rate on your project is 0 . 3 should, you take corrective action on the cost of the project? (
Project management, The schedule progress rate on your project is should, you take corrective action on the cost of the project?
a not necessarily, what i do need to rethink is why the project is behind schedule and take action.
b Yes of course, i have exceed my cost budget.
c The progress rate of the schedule has nothing to do with cost or schedule, it is progress as the name suggests.