Question: PROJECT MANAGEMENT Consider a project with the accompanying Gantt chart. Stella is your only electrical engineer and she is responsible for activities 3 and 4
Consider a project with the accompanying Gantt chart. Stella is your only electrical engineer and she is responsible for activities 3 and 4 , which overlap. Level the project so that Stella is only working a maximum of 8 hours each day. What would the new Gantt chart look like? What would be the new project completion date