Question: Project Managers cannot reduce the project scope and / or quality to reduce the duration of the critical path. This statement is TRUE. FALSE. Overlap

Project Managers cannot reduce the project scope and /or quality to reduce the duration of the critical path. This statement is
TRUE.
FALSE. Overlap sequential activities using finish-to-finish, start-to-start, or startto-finish relationships
FALSE. Use the float in critical path activities
FALSE. Partially overlap sequential activities by using time-leads