Question: Project Managers cannot reduce the project scope and / or quality to reduce the duration of the critical path. This statement is TRUE. FALSE. Overlap
Project Managers cannot reduce the project scope and or quality to reduce the duration of the critical path. This statement is
TRUE.
FALSE. Overlap sequential activities using finishtofinish, starttostart, or starttofinish relationships
FALSE. Use the float in critical path activities
FALSE. Partially overlap sequential activities by using timeleads