Question: Project managers typically use _ _ _ _ _ _ _ _ , also called analogous estimating or the _ _ _ _ _ _

Project managers typically use ________, also called analogous estimating or the ______ method when there is a past history of similar projects and rough-cut estimates are needed for strategic purposes two-to-five years out because, as estimating methods go, it is faster and less expensive. bottom-up, learning curve top-down, phase estimating top-down, range estimating bottom-up, range estimating top-down, apportion