Question: Project managers typically use _ , also called analogousestimating or themethod when there is a past history ofsimilar projects and rough - cut estimates are

Project managers typically use_, also called analogousestimating or themethod when there is a past history ofsimilar projects and rough-cut estimates are needed for strategic purposes two-to-five years out because, as estimating methods go, it is faster and less expensive. bottom-up, range estimating bottom-up, learning curve top-down, apportion top-down, range estimating

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!