Question: Project managers typically use also called analogous estimating or the method when there is a past history of similar projects and rough-cut estimates are needed

Project managers typically use also called

Project managers typically use also called analogous estimating or the method when there is a past history of similar projects and rough-cut estimates are needed for strategic purposes two-to-five years out because, as estimating methods go, it is faster and less expensive. Multiple Choice top-down, apportion bottom-up, range estimating bottom-up, learning curve top-down, phase estimating top-down, range estimating