Question: Project Managment/Operations Management Please help explain step by step. Thank you! The diagram below shows the network describing a certain project. The durations are given

Project Managment/Operations Management Project Managment/Operations Management Please help explain step by step. Thank you! The

Please help explain step by step.

Thank you!

The diagram below shows the network describing a certain project. The durations are given in weeks. Additional information about the project is given in the accompanying table. Determine the normal duration and cost of the project. (ii) Assuming partial crashing is allowed determine the minimum cost of crashing the project duration (a) by 1 week, (b) by 2 weeks (c) by 3 weeks