Question: Project ( mathrm{X} ) has the data points below. Task ( mathrm{Q} ) has a Cost Variance of Negative, 300 Positive, 300 Positive, 2100 Negative,

Project ( mathrm{X} ) has the data points below. Task ( mathrm{Q} ) has a Cost Variance of Negative, 300 Positive, 300 Positive, 2100 Negative, 200 Positive, 200
S Project X has the data points below Task Q has a

S Project X has the data points below Task Q has a Cost Variance of Task BCWS BCWP ACWP 1.000 1,100 1.150 2.000 1,800 2,100 R 1,000 1,200 1,050 2,000 1.900 1,800 O Negative, 300 O Positive, 300 O Positive, 2100 Negative, 200 O Positive, 200