Question: Project Planning Practice Draw or make a Gantt Chart for the following Activities Draw or make Critical Path Method Chart for the following Activities Task
Project Planning Practice
- Draw or make a Gantt Chart for the following Activities
- Draw or make Critical Path Method Chart for the following Activities
| Task | Follows Task | Weeks (duration) | Task Description | Manning Level |
| A | Start | 1 | Site Clearing | 3 |
| B | Start | 0.6 | Obtain lumber and basic materials | 1 |
| C | Start | 2 | Obtain other materials and components | 1 |
| D | B | 2 | Prefabricate wall panels | 4 |
| E | B | 0.9 | Prefabricate roof trusses | 3 |
| F | A,B | 1 | Form and pour footings and floor slab | 3 |
| G | D,F | 0.3 | Erect with Panels | 4 |
| H | E,G | 0.2 | Erect Roof Trusses | 4 |
| J | C,H | 0.5 | Complete Roof | 3 |
| K | J | 2 | Finish Interior | 4 |
| L | J | 1 | Finish Exterior | 2 |
| M | L | 0.4 | Clean up site | 1 |
| N | K,M | 0.2 | Final Inspection and Acceptance | 1 |