Question: Project Scheduling Activity Predecessor(s) Optimistic Most Likely Pessimistic Normal Cost Crash Time Crash Cost A 14 15 16 10,000 14 11,000 B 8 15 16

Project Scheduling

Activity Predecessor(s) Optimistic Most Likely Pessimistic Normal Cost Crash Time Crash Cost
A 14 15 16 10,000 14 11,000
B 8 15 16 9,000 8 15,000
C 5 7 9 7,400 5 10,100
D C 3 7 11 9,600 3 23,200
E C 3 4 17 12,000 3 16,680
F C 3 5 7 8,000 3 16,800
G E,F 1 2 3 11,000 1 13,400
H 2 4 6 12,800 2 27,200
I 3 7 11 6,400 3 14,000
J 4 5 6 9,000 4 15,600
K H,I,J 4 6 14 6,900 4 12,900
L 8 9 16 14,400 8 18,200
M L 3 5 7 13,800 3 15,100
N 4 8 12 10,000 4 24,800
O 5 6 7 9,000 5 19,200
P N,O 1 4 7 7,400 1 17,900
Q P 1 4 7 9,600 1 14,100
R G,Q 1 4 13 12,000 3 16,700

Develop a network drawing and determine the critical path. How long is the business launch expected to take?Case Report

  1. What is the probability for the launch to take longer than 25 days?
  2. Assuming that once the company is in operation, the company will generate $3,000/day in profits. The earlier the company is launched, the earlier they can make these profits. Find the optimal launch time and the optimal costs associated with your proposed launch time.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!