Question: QUESTION THREE [25] The following data relates to a project that you are managing: Time in days Activity Predecessor | Optimistic (a) Most likely Pessimistic

 QUESTION THREE [25] The following data relates to a project that

you are managing: Time in days Activity Predecessor | Optimistic (a) Most

QUESTION THREE [25] The following data relates to a project that you are managing: Time in days Activity Predecessor | Optimistic (a) Most likely Pessimistic (b) (m) A 6 8 15 B A 15 16 22 C A 5 8 12 D A 10 12 18 E B 12 17 23 F C;D 14 16 21 G E 16 18 19 H E 5 10 14 F.H 3 6 J G;H 8 13 17 K I:J 11 15