Question: The following data relates to a project you are working on: Activity Predecessor Most Optimistic Most Likely Most Pessimistic Time in days A - 6

The following data relates to a project you are working on: Activity Predecessor Most Optimistic Most Likely Most Pessimistic Time in days A - 6 8 16 B - 8 10 12 C A 12 14 22 D B 14 17 20 E C;D 13 16 25 F E 15 17 31 G E 5 9 19 H E 7 15 23 I F;H 8 19 36 J G;I 12 18 24 4.1 Using the PERT formula, calculate the time value (t) for each activity. (5) 4.2 Draw the network diagram (AON). (15) 4.3 Identify ALL the paths and indicate the critical path. (5) END OF OPERATIONS AND SUPPLY CHAIN