Question: Project Scheduling Your company is tasked to start a construction project and here are activities and their duration: Activity Description Immediate Predecessors Duration (weeks) A

Project Scheduling

Your company is tasked to start a construction project and here are activities and their duration:

Activity Description Immediate Predecessors Duration (weeks)
A Surveying - 1
B Identify contractors - 4
C Legal works & Permits A 2
D Interview & Select a contractor B 3
E Funding of project A, D 8
F Bring Machinery & Breaking Ground E, C, D 3

A. Draw the Project Network for the project.

B. identify the critical activities.

C. Identify the critical path. Is there one or two critical paths?

D. How long the project will take.

E. How much is the slack for non-critical activities

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!