Question: Project Scheduling Your company is tasked to start a construction project and here are activities and their duration: Activity Description Immediate Predecessors Duration (weeks) A
Project Scheduling
Your company is tasked to start a construction project and here are activities and their duration:
| Activity | Description | Immediate Predecessors | Duration (weeks) |
| A | Surveying | - | 1 |
| B | Identify contractors | - | 4 |
| C | Legal works & Permits | A | 2 |
| D | Interview & Select a contractor | B | 3 |
| E | Funding of project | A, D | 8 |
| F | Bring Machinery & Breaking Ground | E, C, D | 3 |
A. Draw the Project Network for the project.
B. identify the critical activities.
C. Identify the critical path. Is there one or two critical paths?
D. How long the project will take.
E. How much is the slack for non-critical activities