Question: Colonial State College is considering building a new athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office
- Colonial State College is considering building a new athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The activities that would have to be completed before beginning construction are listed next.
Activity | Description | Immediate Predecessors | Time (weeks) |
A | Survey building site | ------ | 6 |
B | Develop initial design | ------ | 8 |
C | Obtain board approval | A,B | 12 |
D | Select architect | C | 4 |
E | Establish budget | C | 6 |
F | Finalize design | D,E | 15 |
G | Obtain financing | E | 12 |
H | Hire contractor | F,G | 8 |
- Develop a network for this project using the AON method.
- Analyze the project network to determine the ET, EF, LS, and LF for each activity. Identify the critical paths.
- Does it appear reasonable that construction could begin 1 year after the decision to begin the project? What is the project-completion time?