During a meeting with some of the project stakeholders, the project manager is asked to add work to the project. scope. The project manager had access to correspondence about the project before the project charter was signed and remembers that the project sponsor specifically denied funding for the scope mentioned by these stakeholders. The BEST thing for the project manager to do is to:
A Let the sponsor know of the stakeholders' request.
B Evaluate the impact of adding the scope.
Tell the stakeholders the scope cannot be added.
D Add the work if there is time available in the project schedule