Question: Project terms Forward Pass - Network calculations to determine earliest Start learliest finish for an activity through working forward through each activity in network. Backward

Project terms
Forward Pass-Network calculations to determine earliest Start learliest finish for an activity through working forward through each activity
in network.
Backward Pass- Network calculations to determine late start/late finish for uncompleted tasks through working backward through each activity in network.
Merge activity: An activity with two or more immediate predecessors
Burst activity: An activity with two or more
immediate successors.
Float: The amount of time an activity may be delayed from its early start withaut delaying the
finish of the project.
Critical Path Method: A network analysis technique used to determine the amount of schedule flexibility network and to determine minimum project duration.
resource-limited schedule start and finish dates reflects expected resaurce availability.
Project terms Forward Pass - Network calculations

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!