Question: Project Time Reduction A project manager wants to compress her project schedule (week). She should compress one time unit (week) per move to reduce the


Project Time Reduction A project manager wants to compress her project schedule (week). She should compress one time unit (week) per move to reduce the project schedule until she reach the has crashed point of the network. The total indirect cost for the project is $2,000 and there is a savings of $100 per time unit reduced. Activi Crash Cost Max CrashTime Normal Time Normal Cost 2 - II II I! II a II .- Answer following questions regarding the project time reduction by 2 weeks (from 20 weeks to 18 weeks)