Question: PS . 7 4 Bell computer is planning to launch a new high - end server. Nine steps or tasks are required to assemble this

PS.74 Bell computer is planning to launch a new high-end server. Nine steps or tasks are required to assemble this computer. Daily demand is expected to be 77 units and there are three 8-hour shifts available each day to meet this production quota.
\table[[Task,Req'd Time (in minutes),Predecessor],[A,14,None],[B,13,A],[C,5,B],[D,4,B],[E,13,A],[F,3,C, D],[G,10,F],[H,15,E],[I,5,G, H]]
What is the total time (in minutes) to produce one server?
What is the takt time (in minutes) for this production line? (Round your answer to a one decimal place.)
What is the theoretical minimum number of workstations required for this production line? (Round up your answer to the nearest whole number.)
After assigning task A to workstation 1, which task (or tasks) should you assign to workstation 2?
B
C
D
E
B or E
C and D
Suppose you assign task B to workstation 2, which task (or tasks) should you then assign to workstation 3?
C,D and F
E(by itself), or C,D and F
E and H
E
C and D
Assume you assign tasks C,D and F to workstation 3, task E to workstation 4, which task (or tasks) should you assign to workstation 5?
G and I
H and I
H
G and H
 PS.74 Bell computer is planning to launch a new high-end server.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!