Question: Q. 1. a. Draw an AON network using the following data and find the probability of completing the path with the longest expected duration in
Q. 1. a. Draw an AON network using the following data and find the probability of completing the path with the longest expected duration in 44 days, the official opening date. [10 Points]
- a = optimistic time estimate
- b = pessimistic time estimate
- m = most likely time estimate, the mode
b. Simulate using Crystal Ball to find the probabilities of project completion. Use a BetaPERT distribution for defining activity time distributions. After a 1,000-trial simulation, examine the statistical information generated and compare the output of the simulation with your findings in section a. Briefly explain the significant similarities and differences. [10 Points]