Question: Q 2 ) : Forward & Backward Pass using PDM / AOA network diagram: table [ [ Activity , table [ [ Depends

Q2): Forward & Backward Pass using PDM / AOA network diagram:
\table[[Activity,\table[[Depends on (Pre-],[Requisite)]],Duration (Days)],[P,,15],[Q,P,8],[R,Q,12],[S,P,7],[T,S,W,13],[U,Qx,17],[V,Q,x,7],[W,V,x,10],[x,R,14]]
Draw the precedence activity network using the given table.
Calculate the earliest and latest start and end dates and the float/slack associated with each activity in the network.