Question: Q# 3. Assume that a project has multiple critical paths. Which one of the following variances should be used to analyze probabilities of different project-completion
Q# 3. Assume that a project has multiple critical paths. Which one of the following variances should be used to analyze probabilities of different project-completion times?
- The critical path with the smallest variance.
- The critical path with the largest variance.
- The sum of variances of all the critical paths.
- The average variance of the critical paths.
- None of the above.