Question: Using the assembly-line balancing procedure, what is the required workstation cycle time in the unit of minute if the production time in minutes per day
Using the assembly-line balancing procedure, what is the required workstation cycle time in the unit of minute if the production time in minutes per day is 431 and the required output per day in units is 41? (Keep two decimal points if applicable .)