Question: Q# 3. Assume that a project has multiple critical paths. Which one of the following variances should be used to analyze probabilities of different project-completion

Q# 3. Assume that a project has multiple critical
Q# 3. Assume that a project has multiple critical paths. Which one of the following variances should be used to analyze probabilities of different project-completion times? a) The critical path with the smallest variance. b) The critical path with the largest variance. c) The sum of variances of all the critical paths. d) The average variance of the critical paths. e) None of the above