Question: Q 3 . Derive a standard time using work sampling. ( 2 5 pt ) Information Source of Data Total time expended by operator (

Q3. Derive a standard time using work sampling. (25 pt)
Information
Source of Data
Total time expended by operator (working time and idle time)
Time cards
Data for One Day
520 min
Number of parts produced
Working time in per cent
Inspection department
Work sampling
300 picces
Idle time in per cent
95%
Average performance index
Work sampling
5%
Total allownaces
Work sampling
120%
Company time study manual
9%
Q 3 . Derive a standard time using work sampling.