Question: Q . 3 . The following table shows for each activity needed to complete the project, the normal time, the shortest time in which the
Q The following table shows for each activity needed to complete the project, the normal time, the shortest time in which the activity can be completed of a building contract and the increase in cost per day for reducing the time of each activity. The contract includes the penalty clause of Rs per day over days. The overhead Indirect Cost per day is Rs The cost of completing the eight activities in normal time is Rs Calculate the lowest cost and the associated project duration. Justify your answer.
tableActivitytableNormaldurationCrash duration,Cost increase day Rstable for first two days each and fornext two days eachtable for first three days each and for next one day