Question: Q . 3 . The following table shows for each activity needed to complete the project, the normal time, the shortest time in which the

Q.3. The following table shows for each activity needed to complete the project, the normal time, the shortest time in which the activity can be completed of a building contract and the increase in cost per day for reducing the time of each activity. The contract includes the penalty clause of Rs 1000 per day over 17 days. The overhead (Indirect) Cost per day is Rs 1600. The cost of completing the eight activities in normal time is Rs.65000. Calculate the lowest cost and the associated project duration. Justify your answer.
\table[[Activity,\table[[Normal],[duration]],Crash duration,Cost increase/ day (Rs.)],[1-2,6,4,500],[1-3,8,4,\table[[400 for first two days each and 900 for],[next two days each]]],[1-4,5,3,300],[2-4,3,3,-],[2-5,5,3,800],[3-6,12,8,\table[[800 for first three days each and 2000],[for next one day]]],[4-6,8,5,500],[5-6,6,6,-]]
(25)
 Q.3. The following table shows for each activity needed to complete

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!