Question: The following table shows for each activity needed to complete the project the normal time, the shortest time in which the activity can be completed
The following table shows for each activity needed to complete the project the normal time, the shortest time in which the activity can be completed of a building contract and the cost per day for reducing the time of each activity. The contract includes a penalty clause of Rs 100 per day over 17 days. The overhead cost per day is Rs 160.

The cost of completing the eight activities in normal time is Rs 6,500.
(a) Calculate the normal duration of the project, its cost and the critical path.
(b) Calculate and plot on a graph the cost/time function for the project and state:
(i) the lowest cost and associated time.
(ii) the shortest time and associated cost.
Activity 1-2 Normal Time in Days Shortest Time in Days Cost of Reduction per Day (Rs.) 80 1-3 1-4 2-4 2-5 68535 3 3. 3 3-6 12 8 4-6 8 5-6 6 56 1888 - 90 30 40 200 50