Question: Q 3 . The time to complete the following project is 1 6 weeks. What is the maximum time that the project can be crashed?

Q3. The time to complete the following project is 16 weeks. What is the maximum time that the project can be crashed? How much would cost increase by?(12 marks)
Activity ABCDEFG
Precedence NormalTime NormalCost Crash Time Crash Cost
--
42200022003126002800
- A
385002300345002600
B C D,E 63490030001400322120042002000