Question: Q 3 Using the information in Table 2 ( 9 marks ) begin { tabular } { | l | l | l |

Q3 Using the information in Table 2
(9 marks)
\begin{tabular}{|l|l|l|r|}
\hline Activity & \multicolumn{1}{|c|}{ Description } & Predecessor(s) & Duration (days)\\
\hline A & Site preparation & None & 4\\
\hline B & Lay foundation & A & 3\\
\hline C & Build walls & B & 5\\
\hline D & Install plumbing & B & 4\\
\hline E & Electrical wiring & C, D & 2\\
\hline F & Painting & C & 3\\
\hline G & Install fixtures & E, F & 3\\
\hline H & Final inspection & G & 1\\
\hline
\end{tabular}
a) Draw A Gantt Chart for the project
(6 marks)
b) If "Install plumbing" is delayed by 2 days, how does this affect the project duration?
(3 marks)
Q 3 Using the information in Table 2 ( 9 marks )

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!