Question: Q 3 Using the information in Table 2 ( 9 marks ) table [ [ Activity , Description,Predecessor ( s ) , Duration (

Q3 Using the information in Table 2
(9 marks)
\table[[Activity,Description,Predecessor(s),Duration (days)],[A,Site preparation,None,2],[B,Lay foundation,A,1],[C,Build walls,B,3],[D,Install plumbing,B,1],[E,Electrical wiring,C, D,2],[F,Painting,C,4],[G,Install fixtures,E, F,5],[H,Final inspection,G,3]]
a) Draw A Gantt Chart for the project
(6 marks)
b) If "Install plumbing" is delayed by 2 days, how does this affect the project duration?
(3 marks)
Q 3 Using the information in Table 2 ( 9 marks )