Question: Q . 4 : A four - phase intersection has critical lane group flow rates for the first three phases of 1 9 0 ,
Q: A fourphase intersection has critical lane group flow rates for the first three phases of
and the saturation flow rates are for all phases. The lost time
is known to be seconds for each phase. If the cycle length is seconds, what is the estimated
effective green time of the fourth phase?