Question: Q1: Draw a CPM network for the problem given in the Table 1.0 below and find critical path and slack time? Predecessor a Activity a

Q1: Draw a CPM network for the problem given in

Q1: Draw a CPM network for the problem given in the Table 1.0 below and find critical path and slack time? Predecessor a Activity a b d e f g h a a b, c d d, e f g, h Duration 5 days 4 3 4 6 4 5 6 6 4