Question: Q19: A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an
Q19:
A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=8.
a.
The critical path is D-F, duration 12.
b.
The critical path is D-E-F, duration 15.
c.
Slack at D is 3 units
d.
Slack at E is 3 units
e.
Slack at E and D = 3 units
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts