Question: A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate

A simple CPM network has three activities, D, E,

A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D = 4, E = 3, F= 8. Which of the following is true? Slack at Eis 3 periods. The critical path is D-E-F, duration 15. Slack at Dis 3 periods. The critical path is D-F, duration 12